Following more than a year of public input, opposition from Council and internal deliberation,
AltaLink informed Crowsnest Pass Municipal Council last week that it would not be relocating the section of line which runs through Frank and along Bluff Mountian.
AltaLink’s Manager of Municipal Relations Kevin Strangway told Council the company had originally intended to move the line off of the side of the mountain and onto the valley floor, closer to the Crowsnest River, but after much opposition on the matter, it decided it would simply update and renovate the existing poles and lines.
Strangway said this project will involve some challenges and interruption in service.
“We have to arrange for interruption that will allow us to take that portion of line out of service for about a week,” said Strangway, adding that the company will reroute feed from B.C. during that time.
Strangway said the project is expected to begin in August, and should be completed by the end of September.